5× Insulated Chiller Body

Customer

Bidfood New Zealand

Product line

Insulated Chiller Body

Fleet

5 units

Chassis

Hino 500 FD 1124

Stage

In Build

Priority

High

Progress · due 23 Sept 2026 (in 26 days)

Design approval gates

5/5 signed off
  1. 1

    Concept & Brief

    Priya Naidu · signed off 28 Jul 2026

    Approved
  2. 2

    Engineering Design

    Tom Whitfield · signed off 29 Jul 2026

    Approved
  3. 3

    Compliance & Certification

    Tom Whitfield · signed off 30 Jul 2026

    Approved
  4. 4

    Customer Sign-off

    David Stanners · signed off 31 Jul 2026

    Approved
  5. 5

    Production Release

    Sione Tuilagi · signed off 01 Aug 2026

    Approved

Job costing (live)

Contract value
$320,000.00
Estimated cost
$215,000.00
Actual labour (401h)
$22,456.00
Actual materials
$68,240.00
Cost to date
$90,696.00
Projected margin
$105,000
32.8% margin

Job pack — bill of materials

8 lines · $122,480
PartCategoryRequiredConsumedLine cost
Barn door pair + hardware Doors & Hardware 5 set 2.8 $4,700
Insulated floor panel 50mm Insulation 100 m2 55 $6,300
PIR insulation panel 75mm Insulation 200 m2 110 $11,600
2K primer 4L Paint & Finish 10 ea 5.5 $960
Topcoat white 4L Paint & Finish 10 ea 5.5 $1,320
FRP composite panel white 2.4m Panel & Sheet 60 sheet 33 $14,700
Carrier Supra 850 unit Refrigeration 5 ea 2.8 $81,000
Reefer control loom Refrigeration 5 ea 2.8 $1,900

Build units

  • Unit 1

    plate pending · 7A901181NZ

    In Build
  • Unit 2

    plate pending · 7A901182NZ

    In Build
  • Unit 3

    plate pending · 7A901183NZ

    In Build
  • Unit 4

    plate pending · 7A901184NZ

    In Build
  • Unit 5

    plate pending · 7A901185NZ

    In Build

Time on this job

401h · $22,456 labour
StaffTaskClock inHoursCost
Sione Tuilagi · Workshop Foreman Finishing & paint 24 Aug, 07:30 am on now
Grant Doyle · Painter / Finisher Fit-out & trim 22 Aug, 07:30 am 80.2h $4,010
Malia Fifita · Refrigeration Technician Electrical & wiring 20 Aug, 07:30 am 80.2h $5,293
Raj Patel · Auto Electrician Refrigeration fit 18 Aug, 07:30 am 80.2h $4,972
Dan Petrović · Fabricator Insulation & lining 16 Aug, 07:30 am 80.2h $4,010
Wiremu Cooper · Fabricator Frame & panel fabrication 14 Aug, 07:30 am 80.2h $4,170

Clock onto this job