2× Refrigerated Truck Body (Reefer)

Customer

Big Chill Distribution

Product line

Refrigerated Truck Body (Reefer)

Fleet

2 units

Chassis

Hino 300 916

Stage

QA

Priority

Standard

Progress · due 01 Sept 2026 (in 4 days)

Design approval gates

5/5 signed off
  1. 1

    Concept & Brief

    Priya Naidu · signed off 01 Aug 2026

    Approved
  2. 2

    Engineering Design

    Tom Whitfield · signed off 02 Aug 2026

    Approved
  3. 3

    Compliance & Certification

    Tom Whitfield · signed off 03 Aug 2026

    Approved
  4. 4

    Customer Sign-off

    David Stanners · signed off 04 Aug 2026

    Approved
  5. 5

    Production Release

    Sione Tuilagi · signed off 05 Aug 2026

    Approved

Job costing (live)

Contract value
$156,000.00
Estimated cost
$104,000.00
Actual labour (378h)
$21,042.00
Actual materials
$55,368.00
Cost to date
$76,410.00
Projected margin
$52,000
33.3% margin

Job pack — bill of materials

9 lines · $61,520
PartCategoryRequiredConsumedLine cost
Door seal EPDM (roll 20m) Doors & Hardware 4 roll 3.6 $472
Foam-in-place kit (2K) Insulation 4 kit 3.6 $1,280
Insulated floor panel 50mm Insulation 48 m2 43.2 $3,024
PIR insulation panel 100mm Insulation 92 m2 82.8 $6,808
2K primer 4L Paint & Finish 4 ea 3.6 $384
Topcoat white 4L Paint & Finish 6 ea 5.4 $792
FRP composite panel white 2.4m Panel & Sheet 28 sheet 25.2 $6,860
Evaporator coil assembly Refrigeration 2 ea 1.8 $4,900
Thermo King T-680 unit Refrigeration 2 ea 1.8 $37,000

Build units

  • Unit 1

    APX-00401 · 7A901121NZ

    Complete
  • Unit 2

    plate pending · 7A901122NZ

    In Build

Time on this job

378h · $21,042 labour
StaffTaskClock inHoursCost
Raj Patel · Auto Electrician Finishing & paint 04 Aug, 07:30 am 63h $3,906
Dan Petrović · Fabricator Fit-out & trim 02 Aug, 07:30 am 63h $3,150
Wiremu Cooper · Fabricator Electrical & wiring 31 Jul, 07:30 am 63h $3,276
Jarrod Klink · Fabricator Refrigeration fit 29 Jul, 07:30 am 63h $3,276
Sione Tuilagi · Workshop Foreman Insulation & lining 27 Jul, 07:30 am 63h $4,284
Grant Doyle · Painter / Finisher Frame & panel fabrication 25 Jul, 07:30 am 63h $3,150

Clock onto this job