2× Refrigerated Truck Body (Reefer)
Customer
Big Chill Distribution
Product line
Refrigerated Truck Body (Reefer)
Fleet
2 units
Chassis
Hino 300 916
Stage
QAPriority
StandardProgress · due 01 Sept 2026 (in 4 days)
Design approval gates
5/5 signed off- 1 Approved
Concept & Brief
Priya Naidu · signed off 01 Aug 2026
- 2 Approved
Engineering Design
Tom Whitfield · signed off 02 Aug 2026
- 3 Approved
Compliance & Certification
Tom Whitfield · signed off 03 Aug 2026
- 4 Approved
Customer Sign-off
David Stanners · signed off 04 Aug 2026
- 5 Approved
Production Release
Sione Tuilagi · signed off 05 Aug 2026
Job costing (live)
- Contract value
- $156,000.00
- Estimated cost
- $104,000.00
- Actual labour (378h)
- $21,042.00
- Actual materials
- $55,368.00
- Cost to date
- $76,410.00
- Projected margin
- $52,000
33.3% margin
Job pack — bill of materials
9 lines · $61,520| Part | Category | Required | Consumed | Line cost |
|---|---|---|---|---|
| Door seal EPDM (roll 20m) | Doors & Hardware | 4 roll | 3.6 | $472 |
| Foam-in-place kit (2K) | Insulation | 4 kit | 3.6 | $1,280 |
| Insulated floor panel 50mm | Insulation | 48 m2 | 43.2 | $3,024 |
| PIR insulation panel 100mm | Insulation | 92 m2 | 82.8 | $6,808 |
| 2K primer 4L | Paint & Finish | 4 ea | 3.6 | $384 |
| Topcoat white 4L | Paint & Finish | 6 ea | 5.4 | $792 |
| FRP composite panel white 2.4m | Panel & Sheet | 28 sheet | 25.2 | $6,860 |
| Evaporator coil assembly | Refrigeration | 2 ea | 1.8 | $4,900 |
| Thermo King T-680 unit | Refrigeration | 2 ea | 1.8 | $37,000 |
Build units
- Complete
Unit 1
APX-00401 · 7A901121NZ
- In Build
Unit 2
plate pending · 7A901122NZ
Time on this job
378h · $21,042 labour| Staff | Task | Clock in | Hours | Cost | |
|---|---|---|---|---|---|
| Raj Patel · Auto Electrician | Finishing & paint | 04 Aug, 07:30 am | 63h | $3,906 | |
| Dan Petrović · Fabricator | Fit-out & trim | 02 Aug, 07:30 am | 63h | $3,150 | |
| Wiremu Cooper · Fabricator | Electrical & wiring | 31 Jul, 07:30 am | 63h | $3,276 | |
| Jarrod Klink · Fabricator | Refrigeration fit | 29 Jul, 07:30 am | 63h | $3,276 | |
| Sione Tuilagi · Workshop Foreman | Insulation & lining | 27 Jul, 07:30 am | 63h | $4,284 | |
| Grant Doyle · Painter / Finisher | Frame & panel fabrication | 25 Jul, 07:30 am | 63h | $3,150 |