6

3× Insulated Chiller Body

Customer

Fonterra Co-operative Group

Product line

Insulated Chiller Body

Fleet

3 units

Chassis

Volvo FL 280

Stage

Complete

Priority

Standard

Progress · due 20 Aug 2026 (8 days ago)

Design approval gates

5/5 signed off
  1. 1

    Concept & Brief

    Priya Naidu · signed off 02 Aug 2026

    Approved
  2. 2

    Engineering Design

    Tom Whitfield · signed off 03 Aug 2026

    Approved
  3. 3

    Compliance & Certification

    Tom Whitfield · signed off 04 Aug 2026

    Approved
  4. 4

    Customer Sign-off

    David Stanners · signed off 05 Aug 2026

    Approved
  5. 5

    Production Release

    Sione Tuilagi · signed off 06 Aug 2026

    Approved

Job costing (actual)

Contract value
$192,000.00
Estimated cost
$129,000.00
Actual labour (525h)
$30,625.00
Actual materials
$73,488.00
Actual cost
$104,113.00
Margin
$87,887
45.8% margin

Job pack — bill of materials

8 lines · $73,488
PartCategoryRequiredConsumedLine cost
Barn door pair + hardware Doors & Hardware 3 set full $2,820
Insulated floor panel 50mm Insulation 60 m2 full $3,780
PIR insulation panel 75mm Insulation 120 m2 full $6,960
2K primer 4L Paint & Finish 6 ea full $576
Topcoat white 4L Paint & Finish 6 ea full $792
FRP composite panel white 2.4m Panel & Sheet 36 sheet full $8,820
Carrier Supra 850 unit Refrigeration 3 ea full $48,600
Reefer control loom Refrigeration 3 ea full $1,140

Build units

  • Unit 1

    APX-00402 · 7A901091NZ

    Complete
  • Unit 2

    APX-00403 · 7A901092NZ

    Complete
  • Unit 3

    APX-00404 · 7A901093NZ

    Complete

Time on this job

525h · $30,625 labour
StaffTaskClock inHoursCost
Malia Fifita · Refrigeration Technician Finishing & paint 09 Jul, 07:30 am 87.5h $5,775
Raj Patel · Auto Electrician Fit-out & trim 07 Jul, 07:30 am 87.5h $5,425
Dan Petrović · Fabricator Electrical & wiring 05 Jul, 07:30 am 87.5h $4,375
Wiremu Cooper · Fabricator Refrigeration fit 03 Jul, 07:30 am 87.5h $4,550
Jarrod Klink · Fabricator Insulation & lining 01 Jul, 07:30 am 87.5h $4,550
Sione Tuilagi · Workshop Foreman Frame & panel fabrication 29 Jun, 07:30 am 87.5h $5,950