2× Rigid Truck Body (Dry Freight)
Customer
Fulton Hogan
Product line
Rigid Truck Body (Dry Freight)
Fleet
2 units
Chassis
Isuzu NPR 400
Stage
CompletePriority
StandardProgress · due 08 Aug 2026 (20 days ago)
Design approval gates
5/5 signed off- 1 Approved
Concept & Brief
Priya Naidu · signed off 03 Aug 2026
- 2 Approved
Engineering Design
Tom Whitfield · signed off 04 Aug 2026
- 3 Approved
Compliance & Certification
Tom Whitfield · signed off 05 Aug 2026
- 4 Approved
Customer Sign-off
David Stanners · signed off 06 Aug 2026
- 5 Approved
Production Release
Sione Tuilagi · signed off 07 Aug 2026
Job costing (actual)
- Contract value
- $92,000.00
- Estimated cost
- $60,000.00
- Actual labour (259.8h)
- $14,375.60
- Actual materials
- $14,508.00
- Actual cost
- $28,883.60
- Margin
- $63,116
68.6% margin
Job pack — bill of materials
8 lines · $14,508| Part | Category | Required | Consumed | Line cost |
|---|---|---|---|---|
| Sub-frame steel channel 100×50 | Chassis Fitment | 16 m | full | $656 |
| Load restraint track (m) | Doors & Hardware | 24 m | full | $456 |
| Roller door assembly 2100×2300 | Doors & Hardware | 2 ea | full | $3,700 |
| Marine ply 18mm 2400×1200 | Flooring | 12 sheet | full | $1,056 |
| Topcoat white 4L | Paint & Finish | 4 ea | full | $528 |
| Aluminium extrusion — corner post | Panel & Sheet | 48 m | full | $1,632 |
| GRP wall sheet lining 1.5mm | Panel & Sheet | 72 m2 | full | $3,024 |
| Zincalume sheet 1.2mm 2400×1200 | Panel & Sheet | 36 sheet | full | $3,456 |
Build units
- Complete
Unit 1
APX-00405 · 7A901041NZ
- Complete
Unit 2
APX-00406 · 7A901042NZ
Time on this job
259.8h · $14,376 labour| Staff | Task | Clock in | Hours | Cost | |
|---|---|---|---|---|---|
| Grant Doyle · Painter / Finisher | Finishing & paint | 29 Jun, 07:30 am | 43.3h | $2,165 | |
| Malia Fifita · Refrigeration Technician | Fit-out & trim | 27 Jun, 07:30 am | 43.3h | $2,858 | |
| Raj Patel · Auto Electrician | Electrical & wiring | 25 Jun, 07:30 am | 43.3h | $2,685 | |
| Dan Petrović · Fabricator | Refrigeration fit | 23 Jun, 07:30 am | 43.3h | $2,165 | |
| Wiremu Cooper · Fabricator | Insulation & lining | 21 Jun, 07:30 am | 43.3h | $2,252 | |
| Jarrod Klink · Fabricator | Frame & panel fabrication | 19 Jun, 07:30 am | 43.3h | $2,252 |